O’Connell Site Services have a wealth of experience providing a professional service to our many customers, which range from uplifting fuel from below ground tanks to excavation works.
The work featured was carried out for a Ministry of Defence site, and took four days to complete. This project involved removal of contaminated water, and then de-gassing using a vacuumed regulated tanker.
The area was CAT scanned and the excavation works commenced, allowing our team to remove a 18,000-litre tank. A soil sample was then taken for the WAC (Waste Acceptance Criteria) test needed, allowing the soil to be returned un-contaminated. On the last day, grass seed was raked in and all plants and fencing was removed ready for the next site.
After this project, O’Connell Site Services was added to the MOD’s tender list, which allowed them to tender for projects in the region of £1,000,000.